Changing the week start date

Support for our integrated Contact Manager, Calendar, and Project Tracker.
Posts: 2
Joined: Thu May 22, 2008 3:46 pm
PostPosted: Thu May 22, 2008 3:51 pm
I am trying to change the week start date from Sunday to Saturday. The scheduling I do has to correlate with my companies work week which is Saturday through Friday. I have tried some changes in the caldatecalc fields, however it alters the functionality between the views. Any help is appreciated.
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Thu May 22, 2008 6:53 pm
This is kind of big change-- so I'm not surprised it's proving difficult. Let me see if I can work it out and post some instructions for how to do it.

Best,

John
John Sindelar
SeedCode
Posts: 2
Joined: Thu May 22, 2008 3:46 pm
PostPosted: Mon Jun 02, 2008 5:24 pm
THANK YOU. I have a temp solution where I created caldatecalc0. Is it possible to change the week number to correlate with my fiscal year which starts February 1st?

Thanks
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Mon Jun 02, 2008 5:54 pm
Hi-- thanks for writing back about this, I'd lost track for a bit.

So this is a much bigger change than I thought-- it's doable, but we have to change about 30 references in the calendar in various scripts and calcs: too much for me to write instructions for.

But I'd be happy to get you a quote for making this change for you (should be about an hour's work) if you'd like to email me directly: john at seedcode.com

I can also get you an estimate for changing the week numbers to match your fiscal year.

Hope that helps,
John Sindelar
SeedCode

Return to SeedCode Calendar

Who is online

Users browsing this forum: No registered users and 2 guests

(855) SEEDCODE
[email protected]
Follow us: