Page 1 of 1
A problem whith Multi-day Events
Posted:
Thu May 06, 2010 5:07 am
by dunumba
Hi John, I have this problem with the calendar:
When a multi-day event finish in the first day of the month and this day is Monday, the name of the event appears during all days of the Month.
What script I have to modify to try it?
Thanks, Dunumba
Posted:
Thu May 06, 2010 7:28 am
by John Sindelar
Hi Dunumba ,
I can't seem to replicate that on my end. Are you sure you're using the latest build? You can find that info here...
http://www.seedcode.com/pmwiki/pmwiki.p ... ionHistory
Hope that helps,
John
Posted:
Thu May 06, 2010 8:12 am
by dunumba
Hi, the version is 5.53...
Posted:
Thu May 06, 2010 8:32 am
by John Sindelar
I'd make the 5.54 changes and see if this persists. Also, what is the date range of the event you're seeing misbehave? I'll try again to reproduce it here.
Posted:
Thu May 06, 2010 9:05 am
by dunumba
In original copy of SC 5.53 the problem does not happen, but on having integrated the calendar in my solution
Posted:
Thu May 06, 2010 9:15 am
by John Sindelar
Makes sense. Think about this: the big variable in the integration is in the fields you add to your events table, and in the mapping you do. Double check the calc fields you added against the ones in our sample file, and check the mapping--especially of the end date-- to be sure you've picked the fields you intended.
Let us know.