Page 1 of 1

Blocks are subdivided and shared under Schedule when 5 min.

PostPosted: Thu Oct 28, 2010 5:50 pm
by SylvieDube
My Calendar starts at 08:00 am and runs until 10:00 pm.

Under the Schedule format, 171 rows have been created per day. I need a daily calendar set to 5 minute increments to see at least 3 lines of information by event of 15 minutes.

Once the information (event details) is added an error begins to appear.

Blocks are subdivided and shared across the calendar. Parts of an event are intertwined with others at the end of the calendar and I found this pattern. When...

Time scale increment is at 15 min. bug start at 25:45 - 8:00 am = 17:45 / 15 min. = 1.11
Time scale increment is at 10 min. bug start at 19:50 - 8:00 am = 11:50 / 10 min. = 1.11
Time scale increment at 5 min. bug start at 13:55 - 8:00 am = 05:55 / 5 min. = 1.11

I do not understand what is causing this effect nor how to solve it.

Advice would be appreciated.


Thank you in avance.

PostPosted: Thu Oct 28, 2010 7:31 pm
by John Sindelar
Hi Sylvie,

Thanks for the post. I'm not sure I follow your description though: can you email a couple screen shots to john at seedcode.com? I'll take a look and let you know what I see.

Thanks!