We have several managers, each watching different projects, and they grow weary of always re-entering that chart setup, for each project every day.
Is there any way to keep the manually entered chart range on a Gantt chart after exit? If the user changes the Red Line dates (1 & 2) it keeps that information, but their custom date ranges disappear upon exit.
Thanks in advance,
JK
Keep Gantt Chart setup
2 posts
• Page 1 of 1
Posts: 7
Joined: Thu Jul 08, 2010 7:26 am |
|
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am |
There is nothing built in to keep this, but since you can load those values from scripts you could create a script that would load a manager's preferred settings or even let them save settings as "views" that they could call up later.