Hi, I built a starter solution using the FREE calendar and have since purchased the PRO calendar to continue working. I have followed the http://www.seedcode.com/pmwiki/pmwiki.p ... ntegration instructions step by step to integrate the PRO calendar into the solution but my calendar is having some problems.
Any Calendar tab I click higher than MONTH tab (such as Year, Schedule, Grid, Gantt...) loops into the "Calendar Helper" window and never completes.
Thanks in advance for any help you can provide. -Charlie
Issues Pasting Pro Calendar into Solution
3 posts
• Page 1 of 1
Posts: 47
Joined: Sun Sep 02, 2007 9:57 am |
Last edited by charliecheney on Tue Mar 22, 2011 9:57 am, edited 1 time in total.
|
Hi Charlie,
A lot of times when we get stuck in those loops, something didn't get set right during the Upon Opening routine, but usually that would apply to all views. Is it possible that the Month view is the only one that should be displaying events? I'd be happy to take a look at your file, and see if it's something that can be fixed easily. You can send it to me at Support at SeedCode.Com -Jason |
|
Posts: 47
Joined: Sun Sep 02, 2007 9:57 am |
Ah cool, thanks Jason, I'll send it to you in email asap.
|