Changed in Calendar Pro 6.25

Support for our integrated Contact Manager, Calendar, and Project Tracker.
SeedCode Staff
SeedCode Staff
Posts: 475
Joined: Wed Jan 02, 2013 11:47 am
PostPosted: Thu Apr 18, 2013 2:00 pm
Overview

Build 6.25 (April 18, 2013) fixes two minor bugs. Below are instructions for making the changes in your file. But before you make these changes, make a backup of your file! Really, do it!

Bug #1: Mini calendar doesn't redraw correctly when switching to a different month on an iPad.

The Fix: Toward the end of the "NinjaCal ( action ; params )" script, in the section following the "stepMonth ( n )" comment, replace these two lines:

Code: Select all
Pause/Resume Script [Duration (seconds): 0]
Freeze Window

...with this:

Code: Select all
If [Get (SystemPlatform) = 3]
  Refresh Window []
Else
  Pause/Resume Script [Duration (seconds): 0]
  Freeze Window
End If

Bug #2: When you initiate a date change in an event from any view other than the Gantt view, the date change doesn't cascade to any other "chained" events from the same project as it should.

The Fix: Toward the end of the "Load Source's FileMaker Fields ( Number )" script, immediately following the "Gantt Chart specific fields follow" comment, delete or disable the 'If [PatternCount ( $$sc_Mode ; "Gantt" )]' step, and its accompanying "End If"

That's it! Enjoy :)