Dragging events to other days with just 1 resource showing

PostPosted: Thu Oct 01, 2015 4:54 am
by timanderson
I think I have found a bug - I hope I am not repeating another report - a quick look did not find it
In Schedule view, with filters set to show only 1 resource it is not possible to drag an event from 1 day to another. As soon as you add another resource to the filters you can drag to another day.

In the DayBack file change the view to Resource - Schedule and 2 days
In the Advanced filters select only Dr. Smith
Try and drag any event to another day - it will not
Go o the Advanced Filters and add Amy Brown
Now you can move Dr. Smith's events to another day

I would apologise, but I know deep down that it is good to get bugs reported, even better to report them fixed!

This applies to 9.52, 9.54 and 9.56. All Mac 10.9.5 - I have not tested on Windows

Thanks

Tim

Re: Dragging events to other days with just 1 resource showi

PostPosted: Thu Oct 01, 2015 8:32 am
by DanW
Hi Tim,

Hope you are well!

Thank you much for digging into DayBack, and for bringing this to our attention.

I will be looking into this and will follow up with your with our findings later today.

Thanks again!

Dan

Re: Dragging events to other days with just 1 resource showi

PostPosted: Thu Oct 01, 2015 1:28 pm
by DanW
Tim,

Thanks again for reaching out and bringing this to our attention. It certainly is a bug! Unfortunately, until this bug gets squashed, there's no direct work around -- other than viewing more than one resource, of course.

Big kudos to you for finding this bug! Again, thanks for sharing what you found with us. And you're right -- it IS good to get bugs reported, so no need to apologize!

Cheers,

Dan

Re: Dragging events to other days with just 1 resource showi

PostPosted: Fri Oct 02, 2015 12:54 am
by timanderson
Thanks for the update Dan. Work around is easy- just involves more clicks- but look forward to the fix.

I can't claim to have found it - one of my clients who is rare in that she is doing thorough testing before final roll-out!

Thanks

Tim

Re: Dragging events to other days with just 1 resource showi

PostPosted: Tue Oct 20, 2015 9:28 am
by tanner
Hi Tim,
Just wanted to let you know that we just released an update for DayBack (9.57) that fixes this issue. You can read about the changes here:

http://www.seedcode.com/pmwiki/index.php?n=DayBackForFileMaker.VersionHistory



Thanks for the bug report so we could get this fixed.

-Tanner

Re: Dragging events to other days with just 1 resource showi

PostPosted: Mon Oct 26, 2015 1:35 am
by timanderson
Thanks Tanner,


done the upgrade and all working now

Thank you

Tim

Re: Dragging events to other days with just 1 resource showi

PostPosted: Mon Oct 26, 2015 8:23 am
by DanW
Tim,

Glad to hear it. Thanks again for the bug report, and pass on our thanks to your client as well!

All the best,

Dan