Keep Gantt Chart setup

Support for our integrated Contact Manager, Calendar, and Project Tracker.
Posts: 7
Joined: Thu Jul 08, 2010 7:26 am
PostPosted: Sun Feb 13, 2011 10:28 am
We have several managers, each watching different projects, and they grow weary of always re-entering that chart setup, for each project every day.

Is there any way to keep the manually entered chart range on a Gantt chart after exit? If the user changes the Red Line dates (1 & 2) it keeps that information, but their custom date ranges disappear upon exit.

Thanks in advance,
JK
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Sun Feb 13, 2011 1:20 pm
There is nothing built in to keep this, but since you can load those values from scripts you could create a script that would load a manager's preferred settings or even let them save settings as "views" that they could call up later.

John
John Sindelar