SeedCodeCalendarComplete

Using The Gantt Chart

Getting Started

When you’re using SeedCode Calendar with its sample data you can explore the Gantt chart by clicking on the Gantt icon in the tool bar (the rightmost icon in the tool bar) if you’re in the Contacts or Projects section, or by clicking on the Gantt tab if you’re in the calendar section.

Once there, use the Project filter to select “The Test Project”. The Gantt chart should snap to the date range of the project, giving you a nice view of it. If it doesn’t, you may need to change a setting. Click the “Chart Setup” button near the bottom of the screen and make sure the very first set of radio buttons (“Use a manually entered chart range…”) is set to “No”.

Once you can see the chart for this project we’d encourage you to play with the zoom and nudge tools at the bottom of the Gantt chart screen.

Setting the Chart Range (the dates)

The Gantt chart has two basic date modes: it can “snap” to the range represented by the chartable data, or it can use any user-defined date range. This behavior is controlled by the first radio button on the chart setup screen. Click the “Chart Setup” button near the bottom of the screen and you’ll see this first set of radio buttons (“Use a manually entered chart range…”).

When this is set to “No”, the Gantt chart will look at the records to be charted and find the earliest start date and the latest end date, using these as the left and right edge dates of the chart. (The chart also looks to see if you have any red target lines set to show and will take their dates into consideration as well.)

Note that once the chart has “snapped” to these dates, you can still use the zoom controls at the bottom of the Gantt chart to zoom in and out or to nudge the chart left or right. Clicking “100%” will re-snap the chart to the left and right dates of the data to be charted.

When “Use a manually entered chart range…” is set to “Yes” the chart will display whatever range you select, regardless of the date ranges depicted in the data being charted. This is especially useful if you want to show sections within a large project (printing just the current month, for instance) or wish to place a short project within the context of a longer time frame. Clicking “100%” in this context will focus the chart back to the dates you entered if you’ve zoomed or nudged the chart.

Note that below the “Use a manually entered chart range…” setting you’ll see some blue text buttons that will easily let you enter some common ranges into the chart’s date filters.

You can also set the chart to use some of these ranges on startup by adjusting the chart’s upon-opening defaults on the Settings section of the Admin tab.

Restricting Chart Content to Items Between Dates

Normally the chart range (the left and right edge of the chart) merely truncate a record’s Gantt bar if the item is outside the chartable range. So that if you have a milestone that only occupies the first week of July, but you’ve nudged your chart to the right so far that you’re only looking at September through November, you’ll still see that milestone’s record, you just won’t see a bar displayed for that milestone.

However, setting the “Restrict Chart Contents…” radio button to “Yes” changes that. (You can find this right below the custom chart range fields on the Chart Setup screen.)

When this is set to “Yes” the left and right chart dates act like filters, omitting or including records as they fall within the chart’s range. This can be a pretty cool way to use the Gantt chart if you have no other filters set. We encourage you to play with this setting to see how it works.

Red Target Lines

The Gantt chart includes the option to display one or two” “target” lines on the chart. Settings for these can be found on the Chart Setup screen (click the “chart setup” button at the bottom of the Gantt chart).

You can use these to show the current date, or to indicate the difference between an earlier deadline and the current deadline.

What Are the Differences Between the Gantt Chart and the Horizontal View of the Scheduling Tab?

The Gantt chart looks very similar to the horizontal view of the scheduling tab- they both have horizontal bars going across the screen- bit the two layouts are fundamentally different and each is best for looking at a certain kind of data.

Time Range

One way to think about this regards the “chartable range”, the amount of time you can see on the chart. On the scheduling screen you can see increments of 5, 15, or 30 minutes, changing that scale up to whole hours or days. You can even set it to whole weeks. You’re looking at 14 “cells” if the chart is set to hours, that is 14 hours. If the chart is set to days, it is two weeks, and if the chart is set to weeks you’re looking at 14 weeks.

The Gantt chart on the other hand doesn’t have a fixed number of cells: it just has a start date on the left and an end date on the right and it shows any activity matching the filters between those dates: the chart range could be 5 days or 5 years. The “100%” button at the bottom of the chart will “snap” the chart to the range of the chartable data as described above, making this very cool for long projects and long range planning.

Content of the Chart

The Gantt chart will show any appointments (activity) matching the filter criteria which is set to show on the Gantt chart (this setting is available for each activity record at the top of the edit appointment mini window). In general, this is used to show project milestones or tasks.

The horizontal scheduling view, on the other hand, shows appointments that a) have a start time and b) are linked to a resource.

You’ll also notice that that horizontal schedule has a fixed number of rows: one for each resource that matches the filter for Resource Type. The gantt chart however, can have thousands of rows if you look at it unfiltered; you’ll almost always want to filter the gantt chart by project or by date range (by clicking the “restrict chart contents” setting on the chart setup screen).

Because of this, you’ll see that bars on the gantt chart never stop and start in the same row: each row is a discrete activity that starts and stops- it never starts again. On the schedule, horizontal bars stop and start within the same resource as the resource is utilized and then is not utilized.

In general, one can think of the schedule view as being used to “scan for gaps” in your schedule, while the gantt chart is used to “gage your progress” toward a deadline.

(855) SEEDCODE
[email protected]
Follow us: