Keep Gantt Chart setup

Support for our integrated Contact Manager, Calendar, and Project Tracker.
Posts: 7
Joined: Thu Jul 08, 2010 7:26 am
PostPosted: Sun Feb 13, 2011 10:28 am
We have several managers, each watching different projects, and they grow weary of always re-entering that chart setup, for each project every day.

Is there any way to keep the manually entered chart range on a Gantt chart after exit? If the user changes the Red Line dates (1 & 2) it keeps that information, but their custom date ranges disappear upon exit.

Thanks in advance,
JK
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Sun Feb 13, 2011 1:20 pm
There is nothing built in to keep this, but since you can load those values from scripts you could create a script that would load a manager's preferred settings or even let them save settings as "views" that they could call up later.

John
John Sindelar
SeedCode

Return to SeedCode Calendar

Who is online

Users browsing this forum: No registered users and 2 guests

cron
(855) SEEDCODE
[email protected]
Follow us: