Changing the week start date

Support for our integrated Contact Manager, Calendar, and Project Tracker.
Posts: 2
Joined: Thu May 22, 2008 3:46 pm
PostPosted: Thu May 22, 2008 3:51 pm
I am trying to change the week start date from Sunday to Saturday. The scheduling I do has to correlate with my companies work week which is Saturday through Friday. I have tried some changes in the caldatecalc fields, however it alters the functionality between the views. Any help is appreciated.
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Thu May 22, 2008 6:53 pm
This is kind of big change-- so I'm not surprised it's proving difficult. Let me see if I can work it out and post some instructions for how to do it.

Best,

John
John Sindelar
SeedCode
Posts: 2
Joined: Thu May 22, 2008 3:46 pm
PostPosted: Mon Jun 02, 2008 5:24 pm
THANK YOU. I have a temp solution where I created caldatecalc0. Is it possible to change the week number to correlate with my fiscal year which starts February 1st?

Thanks
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Mon Jun 02, 2008 5:54 pm
Hi-- thanks for writing back about this, I'd lost track for a bit.

So this is a much bigger change than I thought-- it's doable, but we have to change about 30 references in the calendar in various scripts and calcs: too much for me to write instructions for.

But I'd be happy to get you a quote for making this change for you (should be about an hour's work) if you'd like to email me directly: john at seedcode.com

I can also get you an estimate for changing the week numbers to match your fiscal year.

Hope that helps,
John Sindelar