I have come across a problem with the display of an event in week view.
The event starts on 17th of September and ends on 20th. In month view it displays correctly, but when switching to week view the event extends to 26th Sept. If I move forward the event (with drag and drop) to start on the 18th - finish on 21st, then the week view displays this event correctly.
The problem also occurs if I push back the start date, ie. start on 14th, but it ends on 20th. This does only seem to happen with one of my events, I got other events ending on the 20th but there is no problem.
Your help will be highly appreciated.
Thanks,
Erik
problem with week view
2 posts
• Page 1 of 1
Posts: 1
Joined: Thu Sep 16, 2010 3:30 am |
|
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am |
Hey Erik,
I can't reproduce this as described: creating the 17-20 event and moving to week view offers no problems. The event isn't changed and displays correctly. Could it be that this event has some weird start and end times: things like 3500:00 in the time fields? Try creating a new event from the 17th to the 20th by hand and see if it behaves the same way. If you can't find anything in the original misbehaving event, view that record on the SourceNo 1 layout and see if the timestamps shown for the event match what you'd expect to see. I think you'll find something odd in the data. (and let us know which build number of the calendar you're using). - John John Sindelar
SeedCode |