Gantt Chart
These are the docs for our FM10/11 version of the Pro Calendar. Docs for the newer, FM12 version of our calendar can be found here.
What is the Gantt Chart used for?
The gantt chart was introduced in version 5.6 of the Pro Calendar.
While the gantt chart looks a bit like the calendar's grid view, they are really for different things, and the gantt chart is best at looking at the activities over the course of a project. If you don't have project records in your file, you likely don't need the gantt chart.
On the grid view, each row is a resource in the calendar, so you can have may activities associated with that one resource: this makes the grid view great when you're looking for gaps in your schedule.
Rows on the gantt chart, in contrast, each represent an event, so you,ll never have more than one thing happening in a row.
A few other things to note...
Can I delete the Gantt Chart view if I don't need it?
Absolutely. The gantt chart is just a tab on the calendar: watch this video walkthrough of how to delete that tab from the calendar.
When do items show up on the gantt chart?
When you first arrive at the gantt chart, it will show you all the events which match the active filters occurring in the two weeks starting from the focus date of the calendar. Once you're on the chart, you can select any range of dates you'd like using the default date ranges at the bottom of the screen, or the "custom" range button which let's you type in your own dates.
If some of the events on a project occur before the left hand side of the chart, we'll preface the project or phase name with "..."
Tips & Tricks
Adding fields to the Gantt Chart layout.
The fields on the left side of the gantt chart (the ones on a white background) are simply fields from the CalendarEvents table and you can add any calendar event fields here you'd like. You can also add fields from any of the TOs related to SampleEvents:
Adding rows to the Gantt Chart layout.
You may want to increase the size of the gantt chart by showing more rows, or maybe you'd like to add a scroll bar to it. In this case you can adjust the number of rows that can be displayed at the beginning of the script "Load records into Gantt Chart" by changing the value of the variable $$sc_GanttRows